![Picture](/uploads/2/7/5/5/27553757/8589089.jpg)
Quinn lit blocks used to rise up the perimeter to sole plate level as it is a sloping site.
![Picture](/uploads/2/7/5/5/27553757/8224583.jpg)
The blocks were painted wit a bitumen waterproof-er. The service pipes can be seen here also.
![Picture](/uploads/2/7/5/5/27553757/7937304.jpg)
Concrete slab poured and floated.
![Picture](/uploads/2/7/5/5/27553757/3080862.jpg)
Radon barrier placed on top of concrete slab.
![Picture](/uploads/2/7/5/5/27553757/7922498.jpg)
Kingspan Insulation is being installed under the floor.
![Picture](/uploads/2/7/5/5/27553757/5508296.jpg)
Hole for the radon sump can be seen left exposed here.
![Picture](/uploads/2/7/5/5/27553757/5159520.jpg)
The underfloor pipes laid in the insulation for the Nilan heat recovery system.
![Picture](/uploads/2/7/5/5/27553757/6093552.jpg)
Insulation being placed around and on top of the pipes.
![Picture](/uploads/2/7/5/5/27553757/6398426.jpg)
DPC placed over the insulation ready for the concrete slab.
Concrete slab poured and floated with the services left up through it. Ready for the timber frames.
Timber frames put into position by crane and secured to the floor. Airtight tape and insulation can be seen built into the timber framearound the window opps.
Timber frame from the outside the airtight layer can be seen in red with battens in place on the outside ready for the external panel.
Windows inserted and external panel applied to the battens. Roof being slated with natural slate, picture of lead work in a valley.
More pictures of the external aquapanel. Windows are taped with airtight tape to form the continuous airtight layer around the house.
External insulation placed around the foundation to prevent cold bridge. External render can be seen applied to the aquapanel.
Images of the finished house.